615. The Railway Administrations should make realistic assessment of the amount required
                 for  each  work  in  progress  and  necessary  provision  should  be  made  for  it  in  the  Works
                 Programme.  In  estimating  the  provision  for  works  during  the  budget  year  a  generous
                 allowance  should  be  made  for  those  delays  in  execution  which  though  unforeseen  are
                 known from experience to be so liable to arise particularly prior to inception and during the
                 initial stages of large projects. The provision made should take into account adjustment of
                 charges on surveys connected with a project.

                 616.  In  exhibiting  the  outlay  for  the  current  year  against  individual  works  in  the  works
                 programme,  the  outlay  should  be  as  per  Pink  Book,  and  in  exceptional  cases  where  the
                 Railways  propose  any  substantial  increase  in  the  outlay  with  corresponding  reductions
                 against other  works,  such  revised  outlay  may  be  shown  separately  in  brackets  below the
                 outlay as furnished in the Pink Book duly explaining the reasons for doing so in foot notes at
                 the appropriate places. As far as possible only the last sanctioned cost should be exhibited.
                 Wherever it is visualised that the cost would involve an excess over the last sanctioned cost,
                 effective  steps  should  be  taken  well  in  time  to  have  the  revised  estimates  prepared  and
                 sanctioned by the competent authority before the Works Programme is sent to the Board. In
                 case where the revised estimates are sanctioned  subsequent to the despatch of the final
                 Works Programme but before the end of January of the following year, the same should be
                 promptly advised to the Board to enable the latest sanctioned cost being exhibited in the
                 Pink Book to be circulated along with the Budget. In all cases of revised costs sanctioned by
                 the Board, reference to the letter of sanction should invariably be indicated.

                 617.  Works  once  introduced  through  a  Works  Programme  (including  Track  Renewal
                 Programme)  and  taken  up  after  the  estimates  have  been  sanctioned  by  the  competent
                 authority should continue to be included every year till they are finally completed, except in
                 cases  where  the  works  have  reached  the  completion  stage  and  where  funds  required  if
                 meager, could be found by reappropriation.

                 618. The Works Programs is compiled in the following format:

                                                     Work Programme

                    Demand No. …………………………………………………. (Figures in thousand of rupees)

                 Item   Authority   Particulars   Cost   Expenditure to       Outlay for         Balance
                  No.              of works               end of 3/21    2021-22    2022-23
                   1       2           3          4            5             6          7           8














                     Note: Years have been shown in the form for the purpose of illustration.

                 In respect of "Works in Progress" reference to item No. of the current year's Pink Book and
                 also the authority under which the work was first started should be indicated. The works
                 should be arranged as per the Plan Heads.