Section 2: Estimates

               5.2.1  Code  Rules:  Instructions  regarding  the  different  kinds  of  estimates  and  their
                       preparation  are  contained  in  Chapter  VII  of  the  Indian  Railway  Code  for  the
                       Engineering Department. (Relevant extracts at Annexure: 5-A3)

               5.2.2  General Instructions Applicable to Estimates

                       (a) While preparing the Abstract Estimate in accordance with the Code Rules,
                          the expenditure for Stores may be grouped under Indoor Signallling Equipment,
                          Point mechanism, Colour Light Signals, Cables, Train Detection, Block working,
                          ATP, CTC, Mobile Train Radio Communication, Control Communication etc.
                          besides  Labour,  Tools  and  Plant,  Establishment  Charges,  Freight  and
                          Contingencies, Works to be done by other Departments, e.g. construction of
                          S&T  buildings,  construction  of  staff  quarters,  provision  of  sleepers,  power
                          supply arrangements, etc. are to be included where necessary.


                       (b) While preparing the detailed estimates in accordance with, the Code Rules,
                          the following guidelines shall be observed:


                          (i)  Details  of  cost  of  S&T  Building,  staff  quarters  and  other  buildings  and
                               electric power connections shall be included, by obtaining them from the
                               Departments  concerned  and  shall  be  provided  for  under  separate  sub
                               works.

                          (ii)  Establishment  and  Supervision  charges,  where  necessary,  shall  be
                               included.  Additional  weightage  for  works  to  be  done  under  traffic
                               conditions should be provided.


                          (iii) Provision  shall  be  made  for  additional  quarters  required  for  additional
                               maintenance staff to be posted as a result of the scheme. Provision shall
                               also  be  made  for  additional  Stores/Office  accommodation  where
                               necessary.

                       (c) For preparing estimate for Line Capacity Work, the Traffic Department will
                          advise the Signal and Telecommunication Department of the detailed traffic
                          projections/requirements.  Necessary  feasible  technical  solution  will  be
                          submitted by Signal & Telecommunication department including justification.
                          If the proposed scheme is agreed to by Traffic department. The estimates
                          shall  be  prepared  on  the  basis  of  requirements  furnished  by  the  Traffic
                          Department. The justification for the proposed work will be furnished by the
                          Traffic  Department  together  with  the  anticipated  financial  implications.  A
                          similar  procedure  shall  be  followed  for  works  to  be  executed  for  other
                          departments, e.g. Electrical, Civil Engineering etc.


                       (d) In  regard  to  grouping  of Works,  instructions  contained  in  Para  750  of  the
                          Indian Railway Code for Engineering Department and instructions contained
                          in Para 776 of the Indian Railway Code for finance Department in regard to
                          allocation of charges, shall be observed (relevant extracts at Annexure: 5-A4).






                                              Chapter 5: Planning, Estimating & Survey            Page 86 of 535